Skip to decisions
Žuk — ANTON и JELENA
Back to decisions

Instalments and waiver of accrued interest

Viru Maakohus · First instance

Apartment association bills, payments and debtsDebt claimsLate-payment interest and consequences of delayInstalments and payment schedules

Instalments and waiver of accrued interest

Court order · Viru Maakohus · First instance

Narva linn, Kangelaste prospekt 49 korteriühistu · 80162811

Entry into force has not been reverified

Participants and roles: applicant — Narva linn, Kangelaste prospekt 49 korteriühistu; person concerned, apartment owner — XX

How it started · editorial summary

Owner XX and the association agreed on instalments after the debt claim was contested.

The dispute and the court’s decision

Narva linn, Kangelaste prospekt 49 korteriühistu claimed management-charge arrears and interest from owner XX. Following an objection, the payment-order case was transferred and the claim amended. The court approved the participants’ settlement and terminated proceedings without deciding the original dispute on its merits. XX undertook to pay the debt and 750 euros of the association’s costs in twelve monthly instalments. The association waived accrued interest. Current bills must be paid separately on time. Delay in at least two instalments, or another breach of the instalment condition, allows immediate recovery of the balance and interest at 0.02%; the text specifies no period for that rate. Proper performance leaves no association claim for the period covered by the settlement. Other costs remain with the participants; the appeal period was reduced to one day after service.

Outcome of this decision

Settlement on instalments and costs approved with a waiver of accrued interest; proceedings terminated.
Translation of an anonymised, abridged excerpt from Estonian
2. Terminate proceedings in civil case no. 2-25-102277.