Maintenance debt: award payable in instalments
Editorial summary
The association sought maintenance charges and default interest from XX. The court allowed the admitted claim and ordered EUR 2,068.05 payable in three instalments.
Narva linn, Rahu tn 26 korteriühistu · 80137374
Participants and roles
- Narva linn, Rahu tn 26 korteriühistu — claimant
- XX — defendant
The dispute and the court’s decision
Narva linn, Rahu tn 26 korteriühistu sought apartment maintenance charges and interest from XX. The court entered judgment on admission, awarding EUR 1,947.01 in principal and EUR 121.04 in default interest. It gives no separate substantive reasoning.
The combined EUR 2,068.05 is payable in three equal instalments of EUR 689.35 by 7 March, 7 April and 7 May 2014. Further interest of 0.07% per day runs from 28 February 2014 until the principal is paid, capped at the amount of principal.
The defendant must reimburse EUR 440 in costs: EUR 200 in filing fees and EUR 240 in representation costs, with statutory interest on costs from the judgment taking effect until payment. The judgment is immediately enforceable without security.
Outcome of this decision
EUR 1,947.01 in principal and EUR 121.04 in interest were awarded, with the combined EUR 2,068.05 payable in three instalments of EUR 689.35. Further interest is 0.07% per day capped at the principal; EUR 440 in costs bears statutory interest.