Skip to decisions
Žuk — ANTON и JELENA
Back to decisions

Malmi tn 4: acknowledgment of debt and additional time to pay

Viru Maakohus Narva kohtumaja · First instance

Apartment association bills, payments and debtsDebt claimsInstalments and payment schedulesLate-payment interest and consequences of delay

Malmi tn 4: acknowledgment of debt and additional time to pay

Order approving a settlement · Viru Maakohus Narva kohtumaja · First instance

Narva linn, Malmi tn 4 korteriühistu · 80189939

Entry into force has not been reverified

Participants and roles: Applicant — Narva linn, Malmi tn 4 korteriühistu; Debtor — XX

How it started · editorial summary

After payment-order proceedings began, the association and debtor XX agreed on the acknowledged obligation and additional time to pay.

The dispute and the court’s decision

Narva linn, Malmi tn 4 korteriühistu sought payment of debt and costs through expedited payment-order proceedings. After service of a payment proposal, the participants agreed on the obligation and instalments. Their signed text was submitted for approval and the case transferred from Pärnu Maakohus to Viru Maakohus. On 5 August 2025, the court approved the settlement. XX acknowledged unpaid management costs and accrued late-payment interest; the obligation also includes 25 euros in state fees and 166.80 euros in legal costs. The association granted additional time for fifteen voluntary monthly payments. Breach makes the entire obligation immediately payable. On breach, the association may demand the agreed late-payment interest of 0.02% per day on the originally acknowledged management-cost principal from 1 July 2025. The court found the settlement permissible and enforceable and ended the case. Participants bear other costs. The order does not establish that payments were made.

Outcome of this decision

Approve monthly payment of the acknowledged debt, late-payment interest, 25 euros in state fees and 166.80 euros in legal costs. Breach triggers immediate payment and late-payment interest of 0.02% per day on the originally acknowledged management-cost principal from 1 July 2025. End proceedings.
Translation of an anonymised, abridged excerpt from Estonian
1.4. The debtor acknowledges the obligation specified in clause 1.3 of the settlement. […] 2. End the proceedings in civil case no. 2-25-111135.