Võidu prospekt 13: instalments approved for 619,62-euro balance after partial payment
Narva linn, Võidu prospekt 13 korteriühistu · 80189477
Participants and roles: applicant – Narva linn, Võidu prospekt 13 korteriühistu; interested person XX – debtor and party to the agreement; association’s legal and contractual representatives XX
How it started · editorial summary
After payment order recovery began, the association and debtor XX agreed the balance and six monthly payments. The association confirmed an earlier partial payment.
The dispute and the court’s decision
The court approved the agreement between the apartment association Narva linn, Võidu prospekt 13 and debtor XX for scheduled repayment of the remaining debt and terminated the case. The association initially sought recovery through expedited payment order proceedings. Pärnu Maakohus then ended that procedure and referred the case to Viru Maakohus to approve the agreement.
The debtor acknowledged principal, accrued late-payment interest and 65 euros in costs. The association confirmed an earlier partial payment and agreed the balance with the debtor. The ruling does not establish subsequent compliance with the schedule.
The balance is payable in six monthly instalments. Current association bills must also continue to be paid. Delay entails late-payment interest of 0,022% per day on the unpaid amount.
The court examined the agreement, found it permissible and enforceable, approved its terms on 21 May 2021 and terminated proceedings. The 65 euros in costs included in the agreement form part of the admitted obligation; each participant bears its other costs with no separate mutual reimbursement. The ruling does not set out independent objections to the original charges.
Outcome of this decision
Approve the agreement taking account of the partial payment confirmed by the association. The outstanding debt, late-payment interest and agreed 65 euros in costs are payable in six monthly instalments. Retain current bills and late-payment interest of 0,022% per day on unpaid amounts upon delay. Terminate proceedings; leave other costs with the participants.
Translation of an anonymised, abridged excerpt from Estonian
2. Terminate proceedings in civil case No. 2-21-107646.