The association sued without timely information that the company had paid the debt. The court accepted withdrawal, set aside the default judgment and terminated proceedings, awarding the company 83 euros in partial costs.

Order terminating proceedings following withdrawal · Viru Maakohus Narva kohtumaja · First instance

Narva linn, P. Kerese tn 2 korteriühistu · 80180393

Agarte OÜ · 10369315

Apartment association bills, payments and debtsDebt claimsLate-payment interest and consequences of delay
Participants and roles
  • Claimant — Narva linn, P. Kerese tn 2 korteriühistu
  • Defendant — Agarte OÜ

The dispute and the court’s decision

Narva linn, P. Kerese tn 2 korteriühistu, named in the source as KÜ Narv-Keskring, sued Agarte OÜ for debt and interest on 3 October 2012. After the default judgment of 13 December 2012, the association reported that the company had already paid on 24 September: its accounting service had not informed the board in time. It withdrew before the default judgment entered into force. The court accepted withdrawal, terminated proceedings and set aside the default judgment. The company’s application to reopen the case was left unexamined because, following the withdrawal, it no longer sought a ruling on that application. This did not establish an unpaid debt. Of the company’s claimed costs of 249 euros, the association was ordered to reimburse 83 euros for reviewing the materials and responding to withdrawal. Costs of the reopening application and related defence remained with the company; the association bears its own costs. Refunds were ordered of a 150-euro fee to the association and a 175-euro application security deposit to the company. An order of 2 April 2013 corrected only the mistaken year in this decision’s heading: the correct date is 5 March 2013. All other content remained unchanged. Actual reimbursement and entry into force have not been reverified.

Outcome of this decision

Withdrawal was accepted, proceedings terminated and the default judgment of 13 December 2012 set aside. The company was awarded 83 euros in partial costs; refunds of a 150-euro fee to the association and a 175-euro deposit to the company were ordered. The year was later officially corrected to 2013.

Entry into force has not been reverified

Case history